View the current capital project map.
Looking for information on the Surrey Langley SkyTrain? Visit The Province of BC's official website, surreylangleyskytrain.gov.bc.ca.
The one-way section of Fraser Highway between 204 Street and 206 Street downtown anchors the heart of Langley City's historic core. The purpose of the improvement project is to renew this section, increase the sidewalk widths to improve pedestrian areas and enhance an inviting experience for businesses and visitors.
To date, two rounds of consultation have been completed. Phase One (Appendices) sought input from residents and businesses on what they like and what they would improve in the existing street, while Phase Two (Appendices) asked for feedback on design concepts featuring different parking and public realm options. View the 2024 April Information Meeting Presentation Boards.
Rendering: Click Here
Location: Fraser Highway from 204 Street to 206 Street
Estimated Duration: Fall 2024 - Summer 2025
Estimated Investment: $18 million
Project Details:
- Replace the aging water main and services.
- Replace the aging sanitary, storm sewers, and services.
- New Underground BC Hydro Transmission Infrastructure.
- New streetlights, sidewalks, and concrete curbs.
- New landscaping, including 80 newly planted trees.
Temporary Impacts:
- Through traffic flow prohibitions.
- Phased and intermittent closure of roads and parking, based on construction stages.
- Public walkways and business entries will be available during construction.
Contractor Name: B&B Heavy Civil Construction Ltd.
Location: 56 Avenue from 200 Street to 203 Street
Estimated Completion: Spring 2024
Estimated Investment: $5 million
Project Details:
- Replace the aging water main and services between 200 Street and 203 Street
- Replace the aging storm sewer and services between 200 Street and 203 Street
- Upgrade the existing Traffic Signal on 56 Avenue at 201A Street
Temporary Impacts:
- Partial lane closures for single-lane traffic flow in each direction
- Parking prohibitions
- Intermittent sidewalk and crosswalk closures
City Project Manager: Goran Corda
Contractor Name: McDonald & Ross Construction LTD.
Location: 202 Street Area south of 48 Avenue
Estimated Duration: May to Spring 2025
Estimated Investment: $3.5 million
Project Details:
- Replace the aging water main and services south of 48 Avenue
- Replace the aging storm sewer and services south of 48 Avenue
- Road Paving
Temporary Impacts:
- Localized full road closures with alternate detour routes
- Parking prohibitions
- Localized sidewalk and crosswalk closures
City Project Manager: Ghazal Shirazian
Contractor Name: All Roads Construction
Location: Fraser Highway from Langley Bypass (20800 Block) to Old Yale Road
Estimated Duration: May to Winter 2024
Estimated Investment: $200,000
Project Details:
- Implementation of street-level protected cycling facilities
Temporary Impacts:
- Partial lane closures
- Intermittent sidewalk and closures
- Temporary bike lane closures
City Project Manager: Moudud Hasan
Contractor Name: TBD
Estimated Duration: May to Spring 2025
Estimated Investment: $750,000
Location and Project Details:
- Traffic Signal Upgrades on Fraser Hwy at 200 Street
- Traffic Signal Upgrades on Fraser Hwy at 204 Street
- Traffic Signal Upgrades on Fraser Hwy at 208 Street
- Traffic Signal Upgrades on 56 Avenue at Langley Bypass
- New Traffic Signal on 208 Street at 45A Avenue
Temporary Impacts:
- Temporary lane closures
- Intermittent sidewalk and crosswalk closures
City Project Manager: Moudud Hasan
Contractor Name: TBD
Location: Fraser Highway from 201 A Street to 203 Street
Estimated Completion: Fall 2024
Estimated Investment: $2.2 million
Project Details:
- Replace 340 metres of existing AC water main
- Pavement rehabilitation
Temporary Impacts:
- Traffic lane and sidewalk closures
- Temporary no parking
- Night work at the intersection of Fraser Highway and 203 Street
City Project Manager: Ghazal Shirazian
Contractor Name: TBD
Location: 200 Street from 44 Avenue to 49 Avenue
Estimated Duration: TBD
Estimated Investment: TBD
Project Details:
- Northbound pavement rehabilitation
Temporary Impacts:
- Traffic lane and sidewalk closures
- Temporary no parking
City Project Manager: Ghazal Shirazian
Contractor Name: TBD
Location: Michaud Crescent from 200 Street to 203 Street
Estimated Duration: April 2024 to Fall 2024
Estimated Investment: $2.4 million
Project Details:
- Road rehabilitation and reconstruction
- Replacement of aging water main
- Protected bike lane along the south side
- Intersection safety improvements
- Retention of existing trees and addition of new trees
Temporary Impacts:
- Temporary parking prohibitions along Michaud Crescent
- Sidewalk detours
- Extended closure of the south side
- Construction noise to be expected from 7 am to 7 pm
City Project Manager: Moudud Hasan
Contractor Name: Arsalan Construction LTD.
Location: Michaud Crescent from 53 Avenue to 200 Street
Estimated Completion: Summer 2024
Estimated Investment: TBD
Project Details:
- Paving of existing gravel trail to a 3-metre wide pathway
- Vehicle intrusion deterrent measures
Temporary Impacts:
- Temporary trail closure
- Construction equipment and noise from 7 am to 7 pm
City Project Manager: Moudud Hasan
Contractor Name: TBD
Location: Northwest corner of Douglas Crescent and 203 Street intersection
Estimated Duration: April to Summer 2024
Estimated Investment: $300,000
Project Details:
- Corner reconstruction for pedestrian safety improvement
- Accessibility improvement
- Landscaping improvement
- Traffic signal upgrades
Temporary Impacts:
- Sidewalk closures and detours
- 203 Street Southbound lane closure
- 56 Avenue Westbound curb lane closure
City Project Manager: Moudud Hasan
Contractor Name: Lil Bear Contracting Corp.
Location: Baldi Creek at 200 Street (5400 Block)
Estimated Duration: Summer 2024 to Fall 2024
Estimated Investment: $2 million
Project Details:
- Re-lining of the existing two steel (CSP) deteriorating culverts with HDPE lining
Temporary Impacts:
- Traffic lane and sidewalk closures
City Project Manager: Goran Corda
Contractor Name: TBD
Location: 20650 53A Avenue
Estimated Duration: Summer 2024 to Fall 2024
Estimated Investment: $1 million
Project Details:
- Replace the existing aging suspension bridge with a single-span steel truss bridge
Temporary Impacts:
- Pedestrian bridge closure
City Project Manager: Goran Corda
Contractor Name: TBD
For more information on planning projects and ongoing construction projects in the City, please contact the City Engineering, Parks, and Environment Department at 604.514.2997 or email engineering@langleycity.ca.
For after-hours emergency issues, please call 604.543.6722
The Design Criteria Manual (DCM) outlines the required engineering design and construction standards in the City of Langley for both land developments and all other capital/operating projects in the City. The requirements in the City’s DCM are to be read in conjunction with the City’s Subdivision and Development Servicing Bylaw, 2021, No. 3126.
Check out the Financial Plan for budget information and the list of the City's Capital Improvement Program.