Active
Location
Langley Bypass from 56 Ave to Fraser Highway
Estimated duration
Spring 2026 to December 2026
Estimated investment
$3,600,000
Project details
- Remove bike lanes and move curbs inward to create an asphalt multi-use path for pedestrians and cyclists.
- Connect the active transportation corridor south of Fraser Highway on 208 Street to 56 Avenue.
- Improve safety and vehicle traffic with:
- Repairing asphalt for a smoother driving experience
- New widened and separated multi-use path for cyclists and pedestrians
- Improve traffic flow and safety for pedestrians, cyclists and vehicles with an updated intersection
- Possible repaving of the Langley Bypass, pending assessment.
Temporary impacts
- Lane closures
- Sidewalk closures
- Bike land closures
Contractor name
TBD
City project manager
Jon Bridle
Consultant name: Binnie