204 Street and Logan Avenue Roadworks

Locations
  1. Logan Avenue from 200 Street to the 204 Street Overpass
  2. 204 Street Overpass
Project descriptionAsphalt pavement restoration for improved driving conditions
Current StatusIn construction
Estimated durationAugust 2026 to October 2026
Estimated Investment$1,323,093.00
City project managerNitesh Dugg
ContractorAmrize Canada Inc.
ConsultantRF Binnie and Associates Ltd.

Traffic impacts

  • Project estimated to start mid-August
  • At least one lane in all directions at all times
    • 204 St Overpass (Southbound): Closures allowed 7:00 AM – 3:00 PM
    • Logan Ave (Eastbound): Closures allowed 7:00 AM – 3:00 PM
    • Logan Ave (Westbound): Closures allowed 9:00 AM – 5:00 PM
    • Night Work: Paving from 7:00 PM – 6:00 AM

Full project description

  • Repaving and rehabilitation of Logan Avenue asphalt
  • Provide a smoother driving experience by evening out the existing 204 Street Overpass dip.
  • A total of approximately 16,500 square meters of asphalt will be installed as a part of the project.
204 Street and Logan Avenue Roadworks
204 Street and Logan Avenue Roadwork area
204 Street and Logan Avenue Roadwork area
204 Street and Logan Avenue Roadworks - Capital Project Sign
204 Street and Logan Avenue Roadworks - Capital Project Sign