Completed
Location
Michaud Crescent from 200 Street to 203 Street
Estimated duration
April 2024 to Fall 2024
Estimated investment
$2.4 million
Project details
- Road rehabilitation and reconstruction
- Replacement of aging water main
- Protected bike lane along the south side
- Intersection safety improvements
- Retention of existing trees and addition of new trees
Temporary impacts
- Temporary parking prohibitions along Michaud Crescent
- Sidewalk detours
- Extended closure of the south side
- Construction noise to be expected from 7 am to 7 pm
Contractor name
Arsalan Construction LTD.
City project manager
Moudud Hasan