56 Avenue Water, Storm, and Sanitary Sewer Replacement

Completed
Location
56 Avenue from 200 Street to 203 Street
Estimated duration
Spring 2024
Estimated investment
$5 million
Project details
  • Replace the aging water main and services between 200 Street and 203 Street
  • Replace the aging storm sewer and services between 200 Street and 203 Street
  • Upgrade the existing Traffic Signal on 56 Avenue at 201A Street
Temporary impacts
  • Partial lane closures for single-lane traffic flow in each direction
  • Parking prohibitions 
  • Intermittent sidewalk and crosswalk closures 
Contractor name
McDonald & Ross Construction LTD.
City project manager
Goran Corda
Image
56 Ave map highlighting in dark blue the area that will have sewer replacement work done.