Active
Location
4 Locations (198 Street, 203 Street, 50 Avenue, and 208 Street)
Estimated duration
Fall 2025 to Spring 2026
Estimated investment
$3.5 million for all 4 locations
City project manager
Jon Bridle
Project Details
- Replacement of aging sanitary sewer pipes to enhance water service to residents.
- Reduce water treatment costs by reducing the stormwater and groundwater that flows into the sewers.
- Extend the service life with newer, resilient sanitary sewer pipes.
Impacts To Be Expected
- Construction noise between 7am to 7pm.
- Vehicle traffic between 7am and 3pm along contructions areas and side streets.
- Limited sidewalk closures.
- Traffic control personnel will assist and guide pedestrians.
Project Progress
198 Street (56 Avenue to 53 Avenue)
Estimated completion: Spring 2026
50 Avenue (East of 197 A Street)
Estimated completion: Spring 2026
208 Street (48 Avenue)
COMPLETE!
203 Street (5000 Block)
COMPLETE!