201 Street Storm Sewer Improvements

Location201 Street from Michaud Crescent to 55A Avenue
Project descriptionImprove the City's storm sewer infrastructure to resolve localized flooding and maintenance access issues
Current StatusIn construction
Estimated durationAugust 2026 to Winter 2026
Estimated Investment$924,097.13
City project managerNitesh Dugg
ContractorBlackline Site Works Ltd.
ConsultantISL Engineering and Land Services Ltd.

Traffic impacts

  • Project estimated to start at the end of August
  • Construction will go from 7:00 AM to 7:00 PM as per the noise bylaw
  • Lane closures with single-lane alternating traffic are expected intermittently

Full project description

  • This contract includes capping and abandoning the existing 450mm diameter storm main at 5475 201 Street while preserving the building’s drainage service from the outlet to the onsite manhole.
  • The storm sewer will be rerouted and upsized within the municipal right-of-way, extending a 525mm diameter storm main north along the west side of 201 Street to connect to the existing 750mm diameter system on 55A Avenue.
  • Downstream infrastructure will also be upsized from 750mm diameter to 900mm diameter to accommodate the rerouted flows.
  • The work will improve conveyance capacity, eliminate the storm sewer main on private property, and allow easier access for maintenance purposes

Project images

201 Street Storm sewer upgrade
201 Street storm sewer upgrade area
201 Street Storm sewer upgrade
201 Street storm sewer upgrade area
201 Street Storm Sewer Improvements Capital Project Sign